# Docker patch (bugfix) release process
|
||||
|
||||
Patch releases (the 'Z' in vX.Y.Z) are intended to fix major issues in a
|
||||
release. Docker open source projects follow these procedures when creating a
|
||||
patch release;
|
||||
|
||||
After each release (both "major" (vX.Y.0) and "patch" releases (vX.Y.Z)), a
|
||||
patch release milestone (vX.Y.Z + 1) is created.
|
||||
|
||||
The creation of a patch release milestone is no obligation to actually
|
||||
*create* a patch release. The purpose of these milestones is to collect
|
||||
issues and pull requests that can *justify* a patch release;
|
||||
|
||||
- Any maintainer is allowed to add issues and PR's to the milestone, when
|
||||
doing so, preferably leave a comment on the issue or PR explaining *why*
|
||||
you think it should be considered for inclusion in a patch release.
|
||||
- Issues introduced in version vX.Y.0 get added to milestone X.Y.Z+1
|
||||
- Only *regressions* should be added. Issues *discovered* in version vX.Y.0,
|
||||
but already present in version vX.Y-1.Z should not be added, unless
|
||||
critical.
|
||||
- Patch releases can *only* contain bug-fixes. New features should
|
||||
*never* be added to a patch release.
|
||||
|
||||
The release captain of the "major" (X.Y.0) release, is also responsible for
|
||||
patch releases. The release captain, together with another maintainer, will
|
||||
review issues and PRs on the milestone, and assigns `priority/`labels. These
|
||||
review sessions take place on a weekly basis, more frequent if needed:
|
||||
|
||||
- A P0 priority is assigned to critical issues. A maintainer *must* be
|
||||
assigned to these issues. Maintainers should strive to fix a P0 within a week.
|
||||
- A P1 priority is assigned to major issues, but not critical. A maintainer
|
||||
*must* be assigned to these issues.
|
||||
- P2 and P3 priorities are assigned to other issues. A maintainer can be
|
||||
assigned.
|
||||
- Non-critical issues and PR's can be removed from the milestone. Minor
|
||||
changes, such as typo-fixes or omissions in the documentation can be
|
||||
considered for inclusion in a patch release.
|
||||
|
||||
## Deciding if a patch release should be done
|
||||
|
||||
- Only a P0 can justify to proceed with the patch release.
|
||||
- P1, P2, and P3 issues/PR's should not influence the decision, and
|
||||
should be moved to the X.Y.Z+1 milestone, or removed from the
|
||||
milestone.
|
||||
|
||||
> **Note**: If the next "major" release is imminent, the release captain
|
||||
> can decide to cancel a patch release, and include the patches in the
|
||||
> upcoming major release.
|
||||
|
||||
> **Note**: Security releases are also "patch releases", but follow
|
||||
> a different procedure. Security releases are developed in a private
|
||||
> repository, released and tested under embargo before they become
|
||||
> publicly available.
|